Development Progress
(Swipe the kiri untuk lihat lebih)
RT Progress
Lay Crusher Run Hardcore & Flatten | 14 November 2024
Slab Concrete & Install Underground Pipe | 25 November 2024
Install Underground Pipe | 26 November 2024
Install Roof Beam Formworks | 14 December 2024
Roof Beam Formwork | 26 December 2024
Remove Roof Beam Formwork | 18 January 2025
Brickworks | 28 February 2025
Brickworks | 8 March 2025
3D Model
Project Location
Construction of a Sewage Treatment
Setting Out Progress | 3 August 2024
TNB Stump & Trenches | 16 August 2024
Column Formwork | 26 September 2024
Concrete Footing | 10 Oktober 2024
Ground Beam Formwork | 30 Oktober 2024
Install Underground Pipes | 2 November 2024
Compacted Hardcore & Clean up Ground Beam | 14 November 2024
Installing Floor Beam & Column Rebar | 25 November 2024
Installing First Floor Beam | 26 November 2024
First Floor Slab Formwork | 14 December 2024
Install Slab Formwork | 26 December 2024
Upper Roof Beam Formworks | 18 January 2025
Second Floor Concrete Formwork | 28 February 2025
Upper Roof Beam Concrete | 8 March 2025